RIDF XIX

1. Infrastructural development works in kole wet lands in Thrissur and Malappuram Districts.


Enhancing padyy and vegetable cultivation in the area is the objecive of the project


Project Cost : ₹ 12352 lakh


A.S Order:G.O.(Rt)No. 1501/2013/ AD Dt.20/8/13


Status :Project completed


Major componets :

Deepening -65.373km
Bund formation 134.28km
Construction of Engine Thara- 37 Nos
Construction of Sluices- 30 Nos
Construction of Bridge- 3Nos

Kottyamchira- Kannur

2. Integrated pilot project in Kunnothuparamba, Peringalam, Mokery, Patyam & Kotayam Panchayats in Kannur district.


Aim of project is to improve irrigation facility, enhance paddy cultivation in wet land


A.S Order:G.O.(Rt) No. 63/2013/AD dt.11/01/2013


Status :Project completed


Major componets :

Widening and formation of bund-3900 m
Side protection works with rubble-6700 m
Construction of foot bridge - 1 No (Additional work)
Side protection work with laterate-11080
Construction of VCB - 5no.
Construction of tractor way-6 Silt removal
Constructsion of check dam-3 nos
Construction of Ramp-5no.
Construction of pipe sluice-5 nos.

Renovation of existing drainage system-2x500m

3.Renovation of ponds in drought affected areas of Muthalamada Grama Panchayat in Palakkad district.


Aim of project is to improve irrigation facility, ground water recharge, water con servation


Project cost : ₹ 631.8 lakh


A.S Order:G.O.(Rt) No. 157/2013/AD dt.28/01/2013


Status :Project completed


Major componets :

Deepening of ponds-9
Constrution of 300 mm dia RCC pipe sluice -17 Nos.
Construction of silt collection chamber- 18 nos

4. Infrastructural Development Works for various padasekharams and improvements to drainage system for intensive cultivation in cheppad panchayath in Alappuzha district.


Aim of project :To Protect Paddy Fields from flood, To improve Drainage facility, improve irrigation facility


Project cost : ₹ 335.17 lakh


A.S Order:G.O.(Rt) No. 63/2013/AD dt.11/01/2013


Status :Project completed


Major componets :

Side protection-4300 m(2 x 2150)
RCC Drainage-1170m
culvert-8 nos.
Deepening of Vachal-450m
Slab covering-135 nos.
Leading channel -332m